King Street Sanitary Sewer Relining
Federal contribution
$1.7M
$1,651,005
Federal share33%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Chatham-Kent
- Construction start
- Apr 1, 2010(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast Dec 1, 2009
- Construction end2 weeks earlyforecast Oct 15, 2011
Also in Chatham
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30016 in the federal list. How to read these figures.