Sanitary Sewer Rehabilitation - Community of Tilbury
Federal contribution
$400,000
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Chatham-Kent
- Construction start
- Aug 21, 2010(actual)
- Construction end
- Aug 1, 2011(actual)
Against the original forecast
- Construction start9 months lateforecast Dec 1, 2009
- Construction end2 months earlyforecast Sep 30, 2011