Coutts Line Bridge
Federal contribution
$629,083
Federal share30%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Chatham-Kent
- Construction start
- Aug 2, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2010
Also in Tilbury East
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30043 in the federal list. How to read these figures.