Back to projects

Coutts Line Bridge

Tilbury East, Ontario

completeHighways and RoadsISF
Federal contribution
$629,083
Federal share30%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 2, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2010

Also in Tilbury East

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30043 in the federal list. How to read these figures.