Deer Pit Storm Water Facility

Erin, Ontario

completeWastewaterISF
Federal contribution
$403,334
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Erin
Construction start
Apr 27, 2010(actual)
Construction end
Aug 31, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 2, 2010
  • Construction end4 weeks earlyforecast Sep 30, 2010

Also in Erin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30376 in the federal list. How to read these figures.