Deer Pit Storm Water Facility
Federal contribution
$403,334
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Erin
- Construction start
- Apr 27, 2010(actual)
- Construction end
- Aug 31, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 2, 2010
- Construction end4 weeks earlyforecast Sep 30, 2010
Also in Erin
- Watermain Replacement and Water System Upgrades in the Town of Erin$2.0M
- Erin Community Centre Rehabilitation and Renovation$1.1M
- Replacement of the 8th Line Bridge$550.0K
- Reconstruction of Sideroad 5 - Erin$316.7K
- Install wireless communication plus Supervisory Control and Data Acquisition (SCADA) at multiple Water facilities.$83.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30376 in the federal list. How to read these figures.