Regional Road 97 (Main Street) from Shellard Side Road to East of Franklin Boulevard
Federal contribution
$254,505
Federal share23%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- Aug 31, 2009(actual)
- Construction end
- Oct 1, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2009
- Construction end3 months lateforecast Jun 30, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30406 in the federal list. How to read these figures.