Sale Barn Road
Federal contribution
$4,096
Federal share32%
of $13.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Harris
- Construction start
- Oct 5, 2009(actual)
- Construction end
- Oct 23, 2009(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 15, 2009
- Construction end8 weeks lateforecast Aug 31, 2009
Also in Harris
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30540 in the federal list. How to read these figures.