Sale Barn Road

Harris, Ontario

completeHighways and RoadsISF
Federal contribution
$4,096
Federal share32%

of $13.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Harris
Construction start
Oct 5, 2009(actual)
Construction end
Oct 23, 2009(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 15, 2009
  • Construction end8 weeks lateforecast Aug 31, 2009

Also in Harris

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30540 in the federal list. How to read these figures.