Construction of the Brooklin Community Centre and Library

Brooklin, Ontario

completeRecreationISF
Federal contribution
$4.1M
$4,130,056
Federal share28%

of $14.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Whitby
Construction start
Aug 31, 2009(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30550 in the federal list. How to read these figures.