Wendover Water Pollution Control Plant Upgrade
Federal contribution
$2.2M
$2,190,558
Federal share33%
of $6.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Alfred and Plantagenet
- Construction start
- Aug 16, 2010(actual)
- Construction end
- Oct 26, 2011(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Aug 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30581 in the federal list. How to read these figures.