County Road 41 Reconstruction (7.5 Kilometres)

Addington Highlands, Ontario

completeHighways and RoadsISF
Federal contribution
$2.7M
$2,681,534
Federal share33%

of $8.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 19, 2009(actual)
Construction end
Jul 19, 2010(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Nov 2, 2009
  • Construction end5 months earlyforecast Dec 31, 2010