County Road 41 Reconstruction (7.5 Kilometres)
Federal contribution
$2.7M
$2,681,534
Federal share33%
of $8.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Lennox and Addington
- Construction start
- Oct 19, 2009(actual)
- Construction end
- Jul 19, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Nov 2, 2009
- Construction end5 months earlyforecast Dec 31, 2010
Also in Addington Highlands
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30589 in the federal list. How to read these figures.