Library and Ontario Provincial Police Emergency Services Office
Federal contribution
$333,839
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Southgate
- Construction start
- Oct 5, 2009(actual)
- Construction end
- Jul 1, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Sep 1, 2009
Also in Dundalk
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30607 in the federal list. How to read these figures.