Back to projects

Emergency Helipad Upgrade

Gillies, Ontario

completeRegional And Local AirportsISF
Federal contribution
$9,175
Federal share31%

of $30.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Gillies
Construction start
Nov 3, 2009(actual)
Construction end
Sep 16, 2010(actual)

Against the original forecast

  • Construction end6 weeks earlyforecast Oct 31, 2010