Public Works Garage

North Kawartha, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$315,637
Federal share33%

of $950.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of North Kawartha
Construction start
Aug 7, 2009(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 29, 2009
  • Construction end4 months earlyforecast Mar 31, 2011