Back to projects

Renovations to Community Centre

Carlow/Mayo, Ontario

completeRecreationISF
Federal contribution
$44,064
Federal share29%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Carlow/Mayo
Construction start
Aug 12, 2010(actual)
Construction end
Feb 1, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 10, 2010
  • Construction end5 weeks lateforecast Dec 31, 2010

Also in Carlow/Mayo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30780 in the federal list. How to read these figures.