Eglinton Avenue West - Road Rehabilitation
Federal contribution
$293,318
Federal share22%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Jul 31, 2009(actual)
- Construction end
- May 18, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 15, 2009
- Construction end6 weeks earlyforecast Jun 30, 2010