Mount Brydges Sanitary Sewer Servicing

Mount Brydges, Ontario

completeWastewaterISF
Federal contribution
$2.8M
$2,812,794
Federal share33%

of $8.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
201020112012
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 1, 2010(actual)
Construction end
Jan 6, 2012(actual)

Against the original forecast

  • Construction start9 months lateforecast Nov 15, 2009
  • Construction end3 months lateforecast Sep 30, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30857 in the federal list. How to read these figures.