Mount Brydges Sanitary Sewer Servicing
Federal contribution
$2.8M
$2,812,794
Federal share33%
of $8.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
201020112012
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Strathroy-Caradoc
- Construction start
- Aug 1, 2010(actual)
- Construction end
- Jan 6, 2012(actual)
Against the original forecast
- Construction start9 months lateforecast Nov 15, 2009
- Construction end3 months lateforecast Sep 30, 2011