Lambton County Road 8 Rehabilitation
Federal contribution
$572,106
Federal share30%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Lambton
- Construction start
- Jun 23, 2009(actual)
- Construction end
- Feb 16, 2011(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Aug 1, 2009
- Construction end6 weeks earlyforecast Mar 31, 2011
Also in Brooke-Alvinston
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30870 in the federal list. How to read these figures.