City Centre Transit Priority - Rathburn

Mississauga, Ontario

completePublic TransitISF
Federal contribution
$1.4M
$1,390,000
Federal share33%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Mississauga
Construction start
Aug 28, 2009(actual)
Construction end
Oct 7, 2011(actual)

Against the original forecast

  • Construction start7 months earlyforecast Apr 5, 2010
  • Construction end3 weeks earlyforecast Oct 31, 2011

Also in Mississauga

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30919 in the federal list. How to read these figures.