City Centre Transit Priority - Mavis
Federal contribution
$163,126
Federal share12%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Aug 28, 2009(actual)
- Construction end
- Oct 20, 2011(actual)
Against the original forecast
- Construction start7 months earlyforecast Apr 5, 2010