Rehabilitation of Avening Bridge
Federal contribution
$258,270
Federal share17%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Simcoe
- Construction start
- Apr 5, 2010(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Oct 31, 2011
Also in Clearview
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30960 in the federal list. How to read these figures.