Winston Churchill Boulevard - Road Rehabilitation
Federal contribution
$1.5M
$1,473,976
Federal share30%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Jul 30, 2009(actual)
- Construction end
- May 18, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 15, 2009
- Construction end6 weeks earlyforecast Jun 30, 2010
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30967 in the federal list. How to read these figures.