County Road 5 Resurfacing
Federal contribution
$1.1M
$1,070,000
Federal share33%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- United Counties of Leeds and Grenville
- Construction start
- Aug 5, 2009(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Oct 1, 2009
- Construction end3 months lateforecast Aug 30, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31035 in the federal list. How to read these figures.