Hogg Valley Road Reconstruction
Federal contribution
$650,273
Federal share26%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Tay
- Construction start
- Nov 1, 2009(actual)
- Construction end
- Sep 27, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Oct 15, 2009
- Construction end5 weeks earlyforecast Oct 31, 2011
Also in Tay
- Replacement of watermains on Simcoe, Assiniboia and Alberta Street. Construct storm sewers and replace existing asphalt on Simcoe and Assiniboia Street.$446.6K
- Detailed design and studies component of year-around municipal water services for Grandview Beach and Paradise Point$147.8K
- Port McNicoll Fire Hall Health and Safety Upgrades$141.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31103 in the federal list. How to read these figures.