Hogg Valley Road Reconstruction

Tay, Ontario

completeHighways and RoadsISF
Federal contribution
$650,273
Federal share26%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Tay
Construction start
Nov 1, 2009(actual)
Construction end
Sep 27, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Oct 15, 2009
  • Construction end5 weeks earlyforecast Oct 31, 2011

Also in Tay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31103 in the federal list. How to read these figures.