Lambton County Communications Enhancement
Federal contribution
$100,806
Federal share31%
of $328.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Lambton
- Construction start
- Jul 20, 2010(actual)
- Construction end
- Apr 30, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jul 3, 2010
- Construction end4 weeks lateforecast Mar 31, 2011
Also in Wyoming
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31131 in the federal list. How to read these figures.