Drummond - Concession 1A
Federal contribution
$314,715
Federal share29%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Drummond-North Elmsley
- Construction start
- Aug 19, 2009(actual)
- Construction end
- May 31, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 6, 2009
- Construction end6 months lateforecast Nov 30, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31152 in the federal list. How to read these figures.