Lakeview Branch Library Redevelopment

Mississauga, Ontario

completeCultureISF
Federal contribution
$833,333
Federal share33%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Mississauga
Construction start
Mar 29, 2010(actual)
Construction end
Jun 10, 2011(actual)

Against the original forecast

  • Construction end5 months earlyforecast Oct 31, 2011