Back to projects

Parks and Beaches Beautification

Strong, Ontario

completeRecreationISF
Federal contribution
$33,333
Federal share33%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Strong
Construction start
May 1, 2010(actual)
Construction end
Sep 30, 2010(actual)

Also in Strong