Landfill Site Improvements

Armour, Ontario

completeSolid Waste ManagementISF
Federal contribution
$50,000
Federal share33%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Armour
Construction start
Nov 6, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 1, 2009