Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Hilton
Construction start
Sep 14, 2009(actual)
Construction end
Aug 13, 2010(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 30, 2009
  • Construction end3 months earlyforecast Oct 31, 2010