Casselman Storm Sewers
Federal contribution
$56,892
Federal share7%
of $770.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- United Counties of Prescott and Russell
- Construction start
- Oct 5, 2009(actual)
- Construction end
- Sep 17, 2010(actual)
Also in Casselman
- Construction of New Transmission Lines and Establish New Ground Water Source$3.9M
- Hands free water fountain; renovate to reconfigure space; replace Merv 13 HVAC unit; Other improvements to Air Quality and duct sealing$3.5M
- Construction of a Sewage Collection System for Forest Park Community$978.5K
- Bird's Eye View Park$800.0K
- Hands-free water fountain; Replace Merv 13 HVAC unit; Other improvements to Air Quality and duct sealing$497.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31260 in the federal list. How to read these figures.