Pathway Paving and Lighting Rehabilitation - Stillmeadows Park
Federal contribution
$17,986
Federal share28%
of $64.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Jan 20, 2010(actual)
- Construction end
- Nov 29, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Dec 15, 2009
- Construction end4 months earlyforecast Mar 31, 2011