Public Works Shop and Office Roof
Federal contribution
$10,925
Federal share26%
of $42.0K total eligible cost; the rest comes from other partners.
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Perry
- Construction start
- Aug 17, 2009(actual)
- Construction end
- Aug 21, 2009(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Sep 15, 2009
Also in Emsdale
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31331 in the federal list. How to read these figures.