Pathway Paving and Lighting Rehabilitation - Springbank Meadows

Mississauga, Ontario

completeRecreationISF
Federal contribution
$34,384
Federal share33%

of $104.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Mississauga
Construction start
Mar 2, 2010(actual)
Construction end
Jan 24, 2011(actual)

Against the original forecast

  • Construction end2 months earlyforecast Mar 31, 2011