Pathway Paving and Lighting Rehabilitation - Bloor Athletic Field
Federal contribution
$36,012
Federal share31%
of $114.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Oct 10, 2009(actual)
- Construction end
- Nov 29, 2010(actual)
Against the original forecast
- Construction start2 months earlyforecast Dec 15, 2009
- Construction end4 months earlyforecast Mar 31, 2011
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31346 in the federal list. How to read these figures.