Blyth Campground Event Venue with Washrooms, Showers and Laundry
Federal contribution
$45,675
Federal share33%
of $137.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of North Huron
- Construction start
- Sep 25, 2009(actual)
- Construction end
- May 31, 2010(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Jun 30, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31437 in the federal list. How to read these figures.