Charles Street Reconstruction

Selwyn, Ontario

completeHighways and RoadsISF
Federal contribution
$153,525
Federal share31%

of $502.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Feb 23, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start9 months lateforecast Jun 1, 2009

Also in Selwyn

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31445 in the federal list. How to read these figures.