Pathway Paving and Lighting Rehabilitation - Burnhamthorpe Library Grounds
Federal contribution
$31,566
Federal share33%
of $94.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Sep 2, 2009(actual)
- Construction end
- Apr 30, 2011(actual)
Against the original forecast
- Construction start3 months earlyforecast Dec 15, 2009
- Construction end6 months earlyforecast Oct 31, 2011
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31473 in the federal list. How to read these figures.