Pathway Paving and Lighting Rehabilitation - Sheridan Creek Trail
Federal contribution
$118,149
Federal share31%
of $385.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Oct 10, 2009(actual)
- Construction end
- Nov 29, 2010(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Nov 13, 2009
- Construction end2 weeks earlyforecast Dec 15, 2010