Pathway Paving and Lighting Rehabilitation - Woodeden Park

Mississauga, Ontario

completeRecreationISF
Federal contribution
$47,119
Federal share32%

of $145.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Mississauga
Construction start
Oct 10, 2009(actual)
Construction end
Nov 29, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Nov 13, 2009
  • Construction end2 weeks earlyforecast Dec 15, 2010