St. Alphonse Avenue Reconstruction
Federal contribution
$1.3M
$1,255,000
Federal share33%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Tecumseh
- Construction start
- Aug 4, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 1, 2009
- Construction end4 weeks lateforecast Sep 30, 2011
Also in Tecumseh
- Town of Tecumseh Climate Change & Flooding Resiliency$10.7M
- Reconstruction of the Cedarwood Sanitary Pump Station to mitigate risk of basement flooding during storm events in Tecumseh, Ontario$3.6M
- Reconstruction and Expansion of Two Roads$3.3M
- Lesperance Road & Little River Boulevard Multi-Use Pathway$2.6M
- Construction of the Oldcastle Hamlet Wastewater Servicing System$1.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31609 in the federal list. How to read these figures.