Downtown Collingwood Infrastructure Rehabilitation and Economic Revitalization
Federal contribution
$2.0M
$2,000,000
Federal share29%
of $7.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Collingwood
- Construction start
- Oct 5, 2009(actual)
- Construction end
- Oct 30, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 14, 2009
- Construction end2 months earlyforecast Dec 31, 2010
Also in Collingwood
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31662 in the federal list. How to read these figures.