Government Road Improvements
Federal contribution
$57,372
Federal share33%
of $174.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Johnson
- Construction start
- Aug 1, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Also in Johnson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31667 in the federal list. How to read these figures.