Reconstruction of Matawatchan Road

Denbigh, Ontario

completeHighways and RoadsISF
Federal contribution
$513,165
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Apr 1, 2010(actual)
Construction end
Jun 28, 2010(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 14, 2009
  • Construction end5 weeks earlyforecast Jul 31, 2010

Also in Denbigh

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31735 in the federal list. How to read these figures.