Reconstruction of Matawatchan Road
Federal contribution
$513,165
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Addington Highlands
- Construction start
- Apr 1, 2010(actual)
- Construction end
- Jun 28, 2010(actual)
Against the original forecast
- Construction start6 months lateforecast Oct 14, 2009
- Construction end5 weeks earlyforecast Jul 31, 2010
Also in Denbigh