Brisson Bridge Rehabilitation

Russell, Ontario

completeHighways and RoadsISF
Federal contribution
$338,843
Federal share21%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
May 31, 2010(actual)
Construction end
Jul 8, 2011(actual)

Against the original forecast

  • Construction start2 months earlyforecast Aug 3, 2010
  • Construction end3 weeks earlyforecast Jul 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31766 in the federal list. How to read these figures.