Rehabilitation of Shade Street Bridge

Wilmot, Ontario

completeHighways and RoadsISF
Federal contribution
$242,337
Federal share33%

of $742.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Wilmot
Construction start
May 31, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 12, 2010