Highland Line Improvements

Lanark Highlands, Ontario

completeHighways and RoadsISF
Federal contribution
$484,232
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Nov 23, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start4 months earlyforecast Apr 1, 2010