Rehabilitation of concrete bus stops
Federal contribution
$966,666
Federal share33%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of York
- Construction start
- Sep 8, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Sep 30, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31925 in the federal list. How to read these figures.