Road Resurfacing
Federal contribution
$6,605
Federal share1%
of $480.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
20102011201220132014
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Renfrew
- Construction start
- May 10, 2010(actual)
- Construction end
- Sep 30, 2014(actual)
Against the original forecast
- Construction start6 months lateforecast Nov 1, 2009
Also in Renfrew
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32022 in the federal list. How to read these figures.