Pyne Road Rehabilitation

La Vallee, Ontario

completeHighways and RoadsISF
Federal contribution
$13,523
Federal share24%

of $57.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of La Vallee
Construction start
Aug 25, 2009(actual)
Construction end
Oct 8, 2009(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Sep 10, 2009
  • Construction end8 weeks earlyforecast Nov 30, 2009