Back to projects

Melrose Sand Dome Roof Rehabilitation

Shannonville, Ontario

completeHighways and RoadsISF
Federal contribution
$21,055
Federal share24%

of $86.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Tyendinaga
Construction start
Sep 15, 2009(actual)
Construction end
Nov 15, 2009(actual)

Also in Shannonville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32116 in the federal list. How to read these figures.