Seburn Road Bridge Replacement

Thorold, Ontario

completeHighways and RoadsISF
Federal contribution
$133,234
Federal share30%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Thorold
Construction start
Jul 12, 2010(actual)
Construction end
Oct 18, 2010(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Sep 25, 2010

Also in Thorold

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32127 in the federal list. How to read these figures.